Lockheed Martin's F-35 Lightning II flight test program continues to make progress during the first four months of 2012.
In March, the program completed 123 test flights totaling 223 flight hours, setting a record for the most System Development and Demonstration (SDD) flights and flight hours for a single month.
During the time period, the SDD fleet surpassed the 15,000 total test point threshold, completing approximately 25 percent of the SDD program's entire requirement of more than 59,000 test points. Overall the F-35 test program remains ahead of the 2012 flight test plan, which calls for the accumulation of 1,001 test flights and 7,873 baseline test points as well as additional points beyond the original plan.
Through April 30, the program completed 373 flights against a plan of 281and achieved 2,810 test points - 2,307 of which were baseline points earned against a plan of 2,151. At Eglin Air Force Base, Fla., 30 local area orientation flights were completed totaling 39.5 flight hours as progress toward F-35 pilot training checkout continues.
Another aspect of flight testing is the progressive check out of the latest version of mission system software known as Block 2A. To date, more than 90 percent of Block 2A airborne software code is complete with more than 85 percent of that code currently being flight or lab tested. Block 2A flight test is being conducted at Edwards AFB and will continue through this year. Block 2A is scheduled for "ready for training" in the summer of 2013.
In March, the program completed 123 test flights totaling 223 flight hours, setting a record for the most System Development and Demonstration (SDD) flights and flight hours for a single month.
During the time period, the SDD fleet surpassed the 15,000 total test point threshold, completing approximately 25 percent of the SDD program's entire requirement of more than 59,000 test points. Overall the F-35 test program remains ahead of the 2012 flight test plan, which calls for the accumulation of 1,001 test flights and 7,873 baseline test points as well as additional points beyond the original plan.
Through April 30, the program completed 373 flights against a plan of 281and achieved 2,810 test points - 2,307 of which were baseline points earned against a plan of 2,151. At Eglin Air Force Base, Fla., 30 local area orientation flights were completed totaling 39.5 flight hours as progress toward F-35 pilot training checkout continues.
Another aspect of flight testing is the progressive check out of the latest version of mission system software known as Block 2A. To date, more than 90 percent of Block 2A airborne software code is complete with more than 85 percent of that code currently being flight or lab tested. Block 2A flight test is being conducted at Edwards AFB and will continue through this year. Block 2A is scheduled for "ready for training" in the summer of 2013.